Allis

  • Gym Partition - Remove defunct divider and replace with roll-down curtain
  • Main Entrance - Cover gable end and roof with metal

Cherokee

  • Gym Bleachers - Replace bleachers in main gym
  • Gym Floor - Replace gym floor with cushioned vinyl sport flooring
  • Gym Demo - Demolition of wall tile, bleachers, flooring, movable partition
  • Gym Walls - CMU to be refinished and painted
  • Gym Partition - Replace defunct divider with roll-down curtain
  • Welcome Center - Create a secure entrance sequence at the main entrance to include accessible route from public way and accessible parking
  • Restroom Remodel - Remodel 14 ea School Restrooms

Crestwood

  • Gym Floor Replacement - Replace gym floor with Granite Acoustiflor (Includes mastic abatement, Koster System)
  • Roof Replacement - Roof Sections R04, R06 & R09

District-Wide

  • DDC Upgrade - Transitioning from Legacy to Tridium controllers and upgrading to Tridium in 3 buildings
  • Floor Replacement - 30 classrooms
  • G5 - Emerson, Lincoln, Leopold, Lowell, Muir, and Nuestro Mundo
  • Steam Trap Replacement - Replace steam traps at various sites

Doyle

  • Elevator Replacement - Replace existing traction elevator and all associated equipment and go to a hydraulic  

Elvehjem

  • Welcome Center - Add storefront and hallway access from office

Emerson

  • Concrete Stairs (7th street) - Replace 7th St. concrete stairs
  • Roof Replacement - Roof Sections R01, 03, 04 & R06
  • Restroom Remodel - Remodel 10 ea school restrooms

Falk

  • Cover Fascia Panels - Replace fascia panels with metal cladding
  • Gym Floor - Replace gym floor with cushioned vinyl sport flooring (Koster system)
  • LMC Carpet Replacement - Replace carpet/Paint
  • Replace T12 lights - Replace fixtures with T12 lamps and ballast in the addition areas with new LED fixtures.  T12 parts are no longer made.
  • DDC Upgrade - DDC Siebe conversion

Hamilton

  • Ramp to playground - Redesign and replace the ramp to the playground
  • Roof Replacement - Roof Sections 22, 23
  • Main Office (MS) Flooring Abate/Replace - Welcome Center flooring replacement

Holtzman

  • Full interior renovation

Huegel

  • Replace T12 lights - Replace fixtures with T12 lamps and ballast in the addition areas with new LED fixtures.  T12 parts are no longer made.

Kennedy

  • Boiler Replacement - Replace two obsolete 51 year old Kewanee steam boilers and associated controls- convert to HW boiler system

Lapham

  • Pool Renovation - Pool and Locker Room renovation
  • Roof Replacement - Roof Sections R02, 03, 05 through 09
  • Temperature Control - Convert existing obsolete Siebe DDC control system to Webs DDC

Lowell

  • Restroom Remodel - Remodel 8 ea school restrooms
  • Exterior Masonry - Tuckpointing and Lintel Repair

Mendota

  • Site Improvements Phase 3 - South parking lot and fire lane

Midvale

  • Office Ventilation - Install heating/cooling air handler to serve main office suite
  • Unit Vent Replacement - Replace remaining pneumatic classroom unit ventilators and controls.

Muir

  • Boiler Replacement - Replace boiler #2
  • Roof Replacement - Roof Sections R10, 11, 12, 14, 15, & 16
  • Temperature Control Convert to Webs DDC system.

Pflaum

  • Pave FS Lot/Pflaum Rd. Side - Pave from BS Building along Pflaum to East side border

Sherman/Shabazz

  • Feedwater tank - Replace boiler feedwater tank
  • Chimney Replacement - Remove and rebuild a shorter chimney (abate, remove exist, rebuild, install liner)
  • Roof Replacement - R05,06,07,08,10,11,12,17

Shorewood

  • LMC Carpet - Replacement Replace Carpet/Paint
  • Gym Floor Replacement - Demo and replace gym flooring

Toki

  • LMC Carpet Replacement (Middle School) - Carpet cleaning/Abate/Paint

West

  • Spectator Gymnasium Wood floor - Refinish Wooden Spectator floor

Whitehorse

  • LMC Remodel - Replace Carpet/Paint/Ceilings/Electrical